Over £5m annual Hard FM cost identified and consolidated
Over £1.5m in potential annual savings identified
66% of maintenance activity found to be reactive
Two costed Target Operating Model options delivered in seven weeks
In the past, necessary investment was often put off and by the time it could no longer be avoided, it ended up costing several times more than if it had been addressed at the right time.
Chief Financial Officer, Client Organisation
Define it
Following rapid organic growth, this multi-brand UK hospitality group needed its Facilities Management function to evolve.
Processes, systems and governance had developed at different speeds across the estate, creating fragmented ways of working and a reliance on spreadsheets, manual administration and local knowledge. Compliance depended heavily on manual effort, while the total cost of Hard Facilities Management had never been consolidated.
CI Projects was engaged to assess the current FM operation, quantify the opportunity and design a future-ready Target Operating Model.
Our evidence-led diagnostic included:
- A review of asset management, maintenance, compliance, supply chain and CAFM readiness
- Ten structured interviews with leadership and operational stakeholders
- Analysis of 12 months of payroll and maintenance data
- Design of a future-state structure, governance model and implementation roadmap
The analysis established a true annual Hard FM cost of over £5m, including approximately £2.1m in payroll and £3m in maintenance expenditure.
It also highlighted several underlying challenges:
- A people-dependent operating model
- Limited asset lifecycle management
- A heavily reactive maintenance culture
- Fragmented supplier arrangements
- Limited independent compliance assurance
- Disconnected data held across multiple spreadsheets
A third of rated properties were in the high-risk band for areas including mechanical and electrical plant, roofs, lifts and fire systems. Around £90,000 and several thousand working hours were also estimated to be spent each year on manual logging and administration.
Improve it
CI Projects completed the diagnostic and Target Operating Model design in seven weeks, ahead of the original eight-to-ten-week timeframe.
We designed a future-state operating model focused on:
- A stronger intelligent client function
- Consistent, standards-led delivery
- Whole-life value
- Risk-based independent assurance
- A reliable “golden thread” of asset data
- A scalable, federated FM structure
- Alignment with recognised industry standards
Two fully costed governance options were presented to the board. Each set out the proposed structure, role charters, benefits and risks, giving leaders a clear, evidence-based choice.
CI Projects identified an annual operating-model opportunity of over £1m across workforce planning, procurement, maintenance and asset optimisation.
With 66% of maintenance activity classified as reactive, there was a significant opportunity to move towards a more planned approach. A further potential annual saving of £300,000 to £600,000 was identified across the energy and utilities portfolio through a specialist consultancy partnership. Each opportunity was costed, prioritised and mapped against a phased 20-month implementation roadmap.
Sustain it
The findings were validated with the client throughout the engagement, ensuring the recommendations were accurate, practical and grounded in the organisation’s operating environment.
Phase 1 gave the board:
- A consolidated view of Hard FM costs
- A quantified financial opportunity
- Two costed operating model options
- A clear view of the capabilities required
- A phased route into implementation
After presenting the diagnostic and Target Operating Model, CI Projects developed a costed Phase 2 mobilisation plan. The organisation now has a clear pathway to a more controlled, efficient, and scalable FM service, supported by stronger data, governance, and investment decisions.
Key benefits
- Over £5m annual Hard FM cost made visible in one place
- Over £1.5m potential annual savings identified
- Two independent, board-ready governance options developed
- A clear route from reactive to planned maintenance established
- A costed, phased implementation roadmap produced
- The full diagnostic and design completed in seven weeks