PFI Handback Readiness at Royal Blackburn Hospital

Royal Blackburn Hospital corridor

£1M+ Savings & Recovery Identified

20% Helpdesk Productivity Boost

96% Compliance Performance Achieved

Transformation Roadmap Delivered in 15 Days

Great work. Thanks, CI Projects.

Anonymous

Define it

The Royal Blackburn Hospital PFI Reset & Handback Readiness programme was initiated to address declining performance across hard FM services, driven by complex contractual arrangements, outdated operating processes, inconsistent asset data, and operational inefficiencies. CI Projects was engaged to undertake a Lean Six Sigma review, identify the root causes of performance issues, and develop a practical roadmap that would improve service delivery, strengthen compliance, and support long-term financial recovery.

The hospital was experiencing significant operational and commercial challenges that were impacting service performance and stakeholder confidence. A combination of ageing processes, poor-quality asset data and inconsistent operational practices created barriers to effective contract management and service delivery.

Key issues included:

  • Outdated processes and data management practices affecting compliance and asset performance
  • Repeated service failures resulting in contract deductions and strained relationships between stakeholders
  • No single source of truth for asset information, leading to inefficiencies and increased compliance risks
  • Manual and inconsistent helpdesk and jeopardy management processes that were no longer fit for purpose
  • Low employee morale caused by unclear processes, increasing scrutiny and limited technology adoption

Collectively, these challenges threatened service quality, financial stability and successful preparation for future contract handback requirements.

Improve it

CI Projects acted as both transformation partner and change facilitator, applying Lean Six Sigma methodology to understand the current state, identify improvement opportunities and create a sustainable path forward.

Working closely with operational, commercial and technical stakeholders, we:

  • Facilitated workshops, stakeholder interviews and data validation activities.
  • Conducted end-to-end process reviews to identify inefficiencies, waste and performance barriers.
  • Performed root cause analysis across key workstreams including asset management, lifecycle management, CAFM, commercial operations and helpdesk services.
  • Benchmarked processes and maintenance arrangements against recognised industry standards including SFG20 and HTM guidance.
  • Developed practical recommendations aligned to contractual obligations and operational best practice.

This work provided the evidence base and strategic direction required to support future implementation and operational transformation.

Sustain it

To ensure lasting impact, CI Projects focused on creating a structured improvement roadmap that addressed both immediate operational challenges and long-term capability development.

Key deliverables included:

  • Validation of critical asset management concerns, including the absence of a reliable single source of asset data and misaligned planned maintenance activity.
  • Development of a comprehensive Asset Management Improvement Journey, covering asset strategy, data validation, collection requirements, system setup and maintenance regime redesign.
  • Identification and assessment of commercial risks, including opportunities to recover historical contract losses.
  • Creation of a phased transformation roadmap covering:
    • Asset Management Transformation
    • CAFM Transformation
    • End-to-End Process Redesign
    • SHEQ and Safety Culture Reset
    • Employee Engagement and Change Adoption

The programme established a clear foundation for future improvement activity while enabling the organisation to strengthen governance, compliance and service performance.

More case studies in this sector

Transformation Programme at Guy’s & St Thomas’ NHS Trust

Implementation of best practice standards and processes resulting in c. £300k efficiency savings and improved compliance and assurance.

Patient Catering Transformation across an NHS Trust

The Front of House service was failing, resulting in service failure penalties and impact to patients. CI Projects delivered a full end-to-end transformation.

CAFM System Implementation for Asset Management at Chelsea & Westminster NHS Trust

Saved over 38,400 hours in PPM delivery, equating to a saving of £768k, through setup and structure of asset management data into CAFM as part of transition to in-house service delivery.