Programme relaunched with clear governance
Cross-business alignment on requirements
Governance-approved requirements delivered
Contract-compliant payments solution enabled
Great work, thank you.
Anonymous
Define it
Following rapid growth through both acquisition and organic expansion, Mitie significantly increased the scale and complexity of its capital projects portfolio. However, key financial, commercial and subcontractor management processes remained rooted in a traditional facilities management operating model.
This misalignment created inconsistent financial controls, avoidable commercial risk and inefficiencies across project delivery – particularly around subcontractor payments, cost value reconciliation (CVR) and time capture. As a result, subcontractors were often paid against default terms rather than contractual terms, increasing the risk of disputes, claims and margin erosion.
Mitie needed to relaunch the programme with clarity, rebuild stakeholder confidence and design financial management processes fit for a capital projects business.
Improve it
We led the full redesign of the subcontractor payment, CVR, and time capture processes. This included:
- Working closely with stakeholders across operations, finance, commercial and IT to define requirements appropriate for the scale and complexity of the capital projects business.
- Managing differing stakeholder perspectives through a structured, interactive approach – combining formal workshops with informal discussions to build shared understanding and agreement.
- Developing clear, detailed User Requirements Documents for all three workstreams, enabling governance approval and alignment across the business.
- Collaborating with internal IT teams to design and deliver the new subcontractor payments solution, including system changes, application workflows, UAT and training.
Sustain it
To ensure long-term adoption and consistency, CI Projects:
- Produced Standard Operating Procedures and process diagrams to embed the new ways of working into the organisation’s Quality Management System.
- Created templates to simplify mobilisation and deployment of the new processes on future projects.
Key benefits
- A robust, compliant subcontractor payments solution that ensures subcontractors are paid strictly to their contractual terms.
- Removal of purchase orders for subcontractors, eliminating conflicting terms and reducing commercial exposure.
- Reduced risk of undefendable subcontractor claims through improved applications and payment processes.
- Improved cash flow management and stronger control of variations, supporting better margin performance.
- A successful first phase that establishes the foundation for the business-as-usual team to deliver subsequent phases.